Site condition requirements for small wind power system installation
To successfully install a small domestic wind turbine and ensure its efficient and safe operation, there are clear and strict requirements for the installation site. Before deciding to purchase equipment, a detailed assessment of the target site must be carried out. These conditions are the basis for the success or failure of the project.
1. Core requirements: Superior and stable wind resources
This is the first priority and the most rigid requirement for site evaluation.
Wind speed requirements: The site should have stable and strong wind. Ideally, the annual average wind speed should continuously reach above 4.5 meters/second (about level 3 wind). This is the minimum threshold for wind turbines to be able to generate electricity cost-effectively. Wind speed data should be obtained by measuring with professional wind measuring equipment for at least one quarter at the height where the wind turbine hub is planned to be installed. This is the most reliable method.
Wind farm quality requirements:
Open and unobstructed: The site should be in an open area such as a plain, coastline, hilltop or mountain pass. The horizontal distance between the fan installation point (hub center) and upwind obstacles (such as buildings, woods) should be at least 10 times the height of the obstacles to ensure smooth airflow.
Avoid turbulence: Fans should be kept away from areas that create turbulent airflow, such as immediately behind a building, on the lee side of a steep cliff, or on the edge of dense woods. Turbulence reduces power generation efficiency and increases fatigue and damage to wind turbine structures.
2. Physical space and safe distance requirements
Sufficient and safe physical space must be available for installation and operation.
Tower height and safety radius: In order to obtain better wind resources, the wind turbine needs to be installed on a tower that is high enough. After the height of the tower pole is determined, it must be ensured:
With the tower base as the center and the radius not less than the total height of the tower (including wind turbines), there should be no houses, roads, power lines, public activity areas, etc.
This is to prevent personal injury or property damage in the event that the tower pole collapses, blades or ice blocks fall off.
Foundation and installation space: You need a piece of land that is solid and flat enough to pour a solid concrete foundation (or install cable anchors). At the same time, there needs to be space for hoisting equipment to erect tower poles and install fans.
3. Laws, regulations and community relations
The venue must comply with legal and social norms.
Planning and land consent:
Confirm the nature of the land on the site to ensure it can be used to install such equipment.
Consult local planning, construction, energy and other departments to find out whether construction planning permission, environmental impact assessment and other procedures are required.
Grid connection policy (such as grid connection): If you plan to integrate excess power into the grid, you must apply to the local power grid company in advance to understand the technical requirements and approval process.
Neighborhood and noise considerations: The operation of small wind turbines will produce certain low-frequency noise and visual impact. Communicate with potentially affected neighbors in advance to assess their acceptance and avoid future disputes.
4. Auxiliary facilities and accessibility
Maintenance access: Reliable roads must be available to reach the installation site to facilitate equipment transportation, installation, and future maintenance and inspection.
Distance from energy storage/power consumption point: After the wind turbine generates electricity, it needs to be transported to the controller and battery through cables. The site should not be too far from the power point or energy storage equipment installation point to reduce line losses and cable costs.
Summary: A thorough site assessment is the cornerstone of success
It is important to be both critical and conservative when evaluating site conditions. Even if the wind resources meet the standards, if there are any major obstacles in space, safety or regulations, the project may not be implemented or may have endless consequences.
Suggested action steps:
Preliminary visual inspection: Is the site obviously open and windy all year round?
Professional wind measurement: Hire professionals or rent equipment to conduct on-site wind measurement to obtain reliable data.
Compliance Check: Thoroughly check all regulations and neighborhood requirements.
Comprehensive evaluation: Combine all the above conditions to make a final judgment.
A qualified site is the physical and legal basis for the safe, efficient, and long-term operation of household wind power systems. Its importance is as important as the quality of the equipment itself.
Contact: Zonhan
Tel: 86-13867770817
Whatsapp: 86-13867770817
Email: zonhan@zonhan.com
Add: HEADQUARTERS ECONOMIC PARK, YUEQING,ZHEJIANG,CHINA